Oliver, in short

Yes. A firm that cannot finish its checks must not go ahead, and legal sector guidance says checks must be complete before final agreements are signed and completed. Late source of funds evidence, a change in where the money comes from, or, rarely, a report to the National Crime Agency can all hold up exchange or completion.

Yes. Anti-money laundering checks are not a formality that can be finished after the deal; the law makes them a condition of going ahead.

Why checks can stop the process

  • The firm cannot proceed without them. Under regulation 31 of the Money Laundering Regulations 2017, a firm that cannot complete customer due diligence must not carry out the transaction and must end the relationship.
  • Solicitors and conveyancers are told by the legal sector guidance (LSAG) that checks must be complete before they let funds into client account (other than for fees), allow property to be transferred, or "allow final agreements to be signed and completed".
  • Estate agents must finish their checks on a buyer before a binding contract, which HMRC treats as exchange of contracts.

Typical causes of a late delay

  1. Source of funds evidence sent close to exchange, or a gift where the giver's documents arrive late.
  2. A change to the funding: a new lender, money from a different account, a new gift, or a request to pay from someone else's account.
  3. A mismatch: the money arriving from an account or person that doesn't match what you told the firm.
  4. Rarely, a suspicious activity report. If a firm needs a defence against money laundering from the National Crime Agency (NCA), it must wait up to seven working days for a reply, plus 31 days if consent is refused, and a court can extend that period. LSAG admits it "can be extremely challenging to explain delays to clients" in that situation, because the firm must not tip you off.

Chains are affected too. A delay on one purchase can hold up every sale in the chain, and in a chain each buyer is checked by several firms.

How to avoid it

  • Give full source of funds evidence at the start, not when the completion date is set.
  • Send money only from the account you told the firm about, in your own name.
  • Tell your conveyancer straight away about any change to your funding.
  • Answer questions promptly and directly.

This is general information; if completion is at risk, speak to your conveyancer about options in the contract.

Sources

  1. MLR 2017, regulation 31(1)
  2. LSAG Anti-money laundering guidance for the legal sector (23 Apr 2025), section 6.10 Timing of CDD (source updated 23 April 2025)
  3. HMRC AMLG2200, Estate agent business guidance, section 15 Business relationships (source updated 22 July 2026)
  4. Proceeds of Crime Act 2002, section 335(5), (6) and (6A), 335(5)-(6A)
  5. LSAG guidance (23 Apr 2025), section 11.10.2 What happens after I submit a DAML SAR? (source updated 23 April 2025)

Researched from primary sources and checked by a separate fact-checker. General information, not legal advice.

Still have a question?

Ask Oliver in your own words, or send it to the AML Buddy team and we’ll use it to add a checked answer.

Ask Oliver Email the team
Ask Oliver a follow-upHe has read this page too